top of page

Ssp1: Construction Activity Pollution Prevention Required

Intent

​

To reduce pollution from construction activities by controlling soil erosion, waterway sedimentation and airborne dust generation.

​

Requirements

​

Create and implement an erosion and sedimentation control plan for all construction activities associated with the project. The plan must conform to the erosion and sedimentation requirements of the 2003 EPA Construction

​

General Permit OR local standards and codes, whichever is more stringent. The plan must describe the measures implemented to accomplish the following objectives:

​

  • To prevent loss of soil during construction by storm water runoff and/or wind erosion, including protecting topsoil by stockpiling for reuse.

  • To prevent sedimentation of storm sewers or receiving streams.

  • To prevent pollution of the air with dust and particulate matter.

 

The EPA’s construction general permit outlines the provisions necessary to comply with Phase I and Phase II of the National Pollutant Discharge Elimination System (NPDES) program. While the permit only applies to construction sites greater than 1 acre, the requirements are applied to all projects for the purposes of this prerequisite. Information on the EPA construction general permit is available at http://cfpub.epa.gov/npdes/stormwater/cgp.cfm.

​

Potential technologies & Strategies

​

Create an erosion and sedimentation control plan during the design phase of the project. Consider employing strategies such as temporary and permanent seeding, mulching, earthen dikes, silt fencing, sediment traps and sediment basins.

Project Compliance

​

​FBK Solutions

​

The project has implemented an Erosion and Sedimentation Control (ESC) Plan that conforms to the 2003 EPA Construction General Permit (CGP).

>

  • White Facebook Icon
  • White Instagram Icon
  • White YouTube Icon
  • White Twitter Icon
  • White Vimeo Icon

20-24 Kwai Wing Road, Kwai Chung, NT, HONG KONG | Tel: 2401 6688 | Fax: 2480 5486

bottom of page